Dr Narin Phoawanich, Electricity Generating Authority of Thailand
14–17 September 2026; exact appearance still to resolve
Gastech 2026, BITEC Bangkok — confirmed speaker; EGAT participates in event
Why your time matters
EGAT's Governor is a direct route to distinguish requested data-centre load from committed/energised capacity and identify the system-planning criteria behind connection timing.
What StrataWire still does not know
- How much proposed data-centre load is firm enough to plan around, how much can be energised by requested dates, and what physical or contractual constraint explains the remainder?
Ask these three
1. Of the data-centre electricity demand currently requested from EGAT, how much should Thailand treat as genuinely committed load rather than an application or forecast?
2. What specific grid reinforcement, project-readiness or connection criteria determine whether a requested data-centre energisation date is achievable?
3. What figure should StrataWire track after Gastech to know whether the expected demand is actually materialising?
Challenge cue
Do not let requested MW, signed connection agreements and energised MW collapse into one number. Ask which category every figure represents.